Serbia: EPS begins trial production at newly completed 66 MW Kostolac wind farm

State-owned power utility EPS has confirmed that construction of the Kostolac wind farm has been completed and that the facility has started generating its first megawatt-hours. After receiving approval for grid connection, the first turbine was energized, initiating the project’s trial operation phase. EPS management emphasized that this milestone marks the company’s formal entry into […]

Serbia: EPS begins trial production at newly completed 66 MW Kostolac wind farm Read More »

Serbia: EPS issues tender for supervision of Kostolac 66 MW wind farm construction

Serbia’s state-owned power company EPS has opened a public tender for professional supervision services for the construction of the Kostolac wind farm, with the contract valued at approximately 275,000 euros. The decision follows significant delays and deviations from the original construction timeline, prompting EPS to strengthen oversight to ensure both safety and quality standards are

Serbia: EPS issues tender for supervision of Kostolac 66 MW wind farm construction Read More »

Serbia: Kostolac wind farm to begin trial operations by year-end, adding 66 MW of renewable capacity

State Secretary at the Ministry of Mining and Energy, Sonja Vlahovic, announced that the Kostolac wind farm is on schedule to begin trial operations by the end of the year. All 20 turbines at EPS’ first wind project have now been installed. Once fully operational, the wind farm is expected to generate around 187 million

Serbia: Kostolac wind farm to begin trial operations by year-end, adding 66 MW of renewable capacity Read More »

Serbia: EPS completes wind and solar installations as part of green energy push

Elektroprivreda Srbije (EPS) has successfully completed the installation of the 20th and final wind turbine at its first-ever wind farm in Kostolac, finalizing a renewable energy project with a total capacity of 66 MW. In parallel, all solar panels have been installed at the nearby Petka solar power plant, which is scheduled to be connected

Serbia: EPS completes wind and solar installations as part of green energy push Read More »